Development Review
Review Process |
Administrative Review |
Public Hearing Cases |
---|---|---|
Completeness Check & 1st staff review |
4 weeks |
4 weeks |
Customer review and amended submission |
Varies |
3 weeks |
2nd staff review |
4 weeks |
4 weeks |
Customer review and amended submission |
Varies |
3 weeks |
3rd staff review |
2 weeks |
2 weeks |
Planning Commission Meeting |
N/A |
4 weeks |
City Council |
N/A |
6 weeks |
Total number of weeks |
Varies* |
26 |
*Depends on the amount of time that applicant requires for resubmission.
Public Improvement Plan Review
Review Process |
1- 59 sheets |
60+ sheets |
---|---|---|
Completeness Check |
1 week |
2 weeks |
1st staff review |
2 weeks |
3 weeks |
Collate and Review Staff Report |
1 week |
1 week |
Customer review and revisions |
4 weeks |
6 weeks |
2nd staff review |
3 weeks |
5 weeks |
Customer review and revisions |
3 weeks |
5 weeks |
Final staff review and approval |
1 week |
2 weeks |
Total number of business days |
56 |
77 |
Total number of weeks |
11.2 |
15.4 |
Note: Please contact Engineering Services for estimated timeline if your plan set is 80+ sheets.
Building Plan Review
Commercial & Multi-Family |
||||
---|---|---|---|---|
Review Process |
Tenant Finish |
Single Family |
1 - 100 Sheets |
100+ |
Staff review for code compliance |
4 weeks |
4 weeks |
4 weeks |
6 weeks |
Customer review and code corrections |
2 weeks |
2 weeks |
2 weeks |
4 weeks |
Staff review for code compliance |
2 weeks |
2 weeks |
2 weeks |
4 weeks |
Total number of business days |
40 |
40 |
40 |
70 |
Total number of weeks |
8 |
8 |
8 |
14 |
Notes: Most residential projects under $30K can be reviewed immediately at the building counter on the second floor at City Hall; Building permits cannot be issued until all Development Review processes are complete.
Site and Stormwater Review
Review Process |
1-5 sheets |
1-10 sheets |
11+ sheets |
---|---|---|---|
1st staff review |
3 weeks |
3 weeks |
4 weeks |
Customer review and revisions |
3 weeks |
3 weeks |
4 weeks |
2nd staff review |
3 weeks |
3 weeks |
4 weeks |
Customer review and revisions |
3 weeks |
3 weeks |
4 weeks |
Final staff review and approval |
2 weeks |
2 weeks |
3 weeks |
Total number of business days |
56 |
56 |
77 |
Total number of weeks |
11.2 |
11.2 |
15.4 |